Metrics#

There are multiple metrics that the optimizers can compute. We can separate these metrics into 3 classes:

  • Matrix Metrics: All metrics that can be computed from the N-1 matrix
  • Operation Metrics: Metrics that are dictated by operation and not a result of the loadflow computation
  • Other Metrics: Various other metrics

Some metrics are exclusive to one stage (ac/dc) and some are feasible on both stages. Generally, Matrix Metrics and Operation Metrics are feasible on both stages while for other metrics it depends.

All N-0 metrics operate on the base case (no contingency), while N-1 metrics consider all contingencies. DC metrics use the imported artificial limits of monitored branches, not physical equipment limits. Results generated before this change are not directly comparable without accounting for the different thresholds.

Matrix Metrics#

  • max_flow_artificial_limit_n_0 / max_flow_artificial_limit_n_1: The maximum flow on any branch in fractions. For N-0 this is the base case, for N-1 this considers all contingencies. A value of 1.1 means the highest loaded branch is 10% above its limits.
  • median_flow_artificial_limit_n_0 / median_flow_artificial_limit_n_1: The median relative flow across all branches. For N-1, considers the worst contingency for each branch. Provides a measure of overall grid loading.
  • overload_energy_artificial_limit_n_0 / overload_energy_artificial_limit_n_1: Total amount of energy (in MW) that exceeds artificial limits, summed across all timesteps and overloaded branches. For N-1, considers the worst contingency for each timestep. High voltage branches dominate this metric as they carry more MW, so the optimizer prioritizes these. Can optionally apply per-branch weights via overload_weight.
  • underload_energy_artificial_limit_n_0 / underload_energy_artificial_limit_n_1: Total unused capacity (in MW) below branch ratings. Indicative of how much flow can still be pushed through the grid, but is no sensible optimization metric. Use for debugging purposes only.
  • exponential_overload_energy_artificial_limit_n_0 / exponential_overload_energy_artificial_limit_n_1: Exponentially weighted overload energy (default α=1.5) that more heavily penalizes severe overloads. Branches loaded at 150% contribute more than proportionally compared to those at 110%.
  • critical_branch_count_artificial_limit_n_0 / critical_branch_count_artificial_limit_n_1: The number of branches that are overloaded in the worst timestep. For N-1, counts branches overloaded in at least one contingency. Targeting this metric will incentivize the optimizer to concentrate the overload onto fewer lines, which might be easier to redispatch than many overloaded lines at the same time.
  • cumulative_overload_artificial_limit_n_0 / cumulative_overload_artificial_limit_n_1: Sum of relative overload percentages across all branches. Unlike overload energy, this metric treats all branches equally regardless of their capacity - a 10% overload on a small line contributes the same as on a large line.
  • top_k_overloads_artificial_limit_n_1: Returns information about the k worst N-1 contingencies including their relative overloads and identifiers. This is used internally for the early stopping feature and should not become an optimization metric. For debugging purposes, plotting might be interesting.

Operation Metrics#

These metrics measure operational aspects of the topology rather than electrical flows:

  • switching_distance: Total number of reassignments required to reach the topology from the initial state, computed using reassignment_distance information. Measures the number of switching operations needed. Note that currently, the AC solver counts this slightly differently than the DC solver. This is a bug, not a feature.
  • split_subs: Number of substations that have been split into multiple busbars. Higher values indicate more complex substation configurations.
  • disconnected_branches: Number of branches (lines/transformers) that have been intentionally disconnected in the topology.
  • pst_switching_distance_squared: Squared sum of absolute distances from the initial PST setpoints to the current optimized ones.
  • pst_switching_distance: Linear distance from the initial PST setpoints to the current optimized ones, computed as the sum of absolute tap changes.
  • pst_activated: Number of PST tap positions that differ from their initial tap position (implicit unit cost). This counts changed PST setpoints and can be weighted in target_metrics.

Other Metrics#

  • n0_n1_delta: Penalty for exceeding the maximum allowed flow change between N-0 and N-1 cases. Computed as the sum of MW exceeding n0_n1_max_diff limits across all branches and timesteps. Useful for operational constraints that limit how much flow can shift during contingencies.
  • cross_coupler_flow: Penalty for violating maximum cross-coupler flow limits in split substations, summed across all splits and timesteps. Enforces limits on power flow between busbars within a substation. A high penalty will incentivize the optimizer towards more symmetric splits as symmetric splits tend to have low cross coupler flows.
  • n_2_penalty: Penalty value for N-2 contingency violations, if N-2 analysis is enabled. Higher values indicate more severe or more frequent N-2 issues.
  • bb_outage_penalty: Penalty for busbar outage scenarios. Only relevant when busbar outage analysis is included. This is the difference between the busbar outage overload energy before the optimization and after the optimization, meaning it is 0 if the topology is either equal or better under busbar outages.
  • bb_outage_overload: Maximum overload observed during busbar outage scenarios. This is in case the bb outages are to be counted as normal outages and should be added to the overall overload energy.
  • bb_outage_grid_splits: Number of grid splits (islands) created during busbar outage scenarios. These bb cases did not compute anything sensible, if this number is high check the bb outage preprocessing. Ideally it should be 0 at all times.
  • max_va_diff_n_0 / max_va_diff_n_1: Maximum absolute voltage angle difference across any branch. AC analysis only.
  • critical_va_diff_count_n_0 / critical_va_diff_count_n_1: Number of (timestep, element) groups whose maximum absolute voltage angle difference across contingencies exceeds a configurable threshold. AC analysis only.
  • voltage_jump_count_n_1: Number of bus voltages that jumped by more than X% between their N-0 voltage and their N-1 voltage. AC analysis only.
  • \<family>_permanent_n_0 / \<family>_permanent_n_1 (AC only): The AC variants of max_flow, overload_energy, overload_current (overload in A rather than MW) and critical_branch_count, measured against the physical limits of all monitored branches (permanent_limit, for N-0 and N-1). If the results have no limit table, the loading column is used, which is relative to the physical limit.
  • \<family>_artificial_limit_n_0 / \<family>_artificial_limit_n_1 (AC only): The same families measured against the artificial limits (artificial_limit_n_0 / artificial_limit_n_1), which only exist for optimized and non-worsening branches. These match the DC solver metrics. They are None if no branch has the limit or the results have no limit table. The AC optimizer reads the scope set by limit_scope (default artificial_limit) and raises if its metrics are None.
  • non_converging_loadflows: The number of loadflow cases (N-0 or N-1) that did not converge. In the DC optimizer, this value is always 0 as either the entire loadflow converges or the solver returns a separate success flag which invalidates all other returns. On AC this is not the case, so this metric is useful to track.
  • fitness_dc: Legacy fitness metric for DC stage. TODO: Remove when Topology is refactored to accept different stages like "dc", "dc+" and "ac".